AGI, Abbie Gregg, Inc.
 

University of California Davis | Kemper Hall
Cleanroom Renovation

     
  Project Features:
> 26 new or relocated tools, 14 added to the Main Nanofab Cleanroom.
> Basement Room 79, 800 SF, Characterization lab with approximately 8 tools.
> 1,000 SF relocated offsite 3 sites studied for MOCVD Growth Lab.
> Fast Track project with multiple bid packages.
  Project Location:
> Davis, California
   
  Project Size:
> 14,000 sq ft total
   
  Architectural Firm of Record:
> Abbie Gregg, Inc.
   
  Engineering Firm of Record:
> Abbie Gregg, Inc.
   
  Professional Services Completed:
> 2017
   
  Project Status:
> Construction completed in 2017
   
   
  Services Provided by AGI for Project:
> Site Tour of proposed spaces
> Hazardous Process Materials Study with Code Analysis
> High Level Site Assessment Study Report
> Test to Fit Verification
> Cost Benchmarking for equipment, tools and construction
> Preliminary ROM / Cost Estimates
> Full Design Services Programming through Construction Documents
> Tool Hook-Up Design
> Construction Administration Services
> Feasibility Study for Offsite Growth Lab
> Structural Bracing Designs
> Demolition Designs and Abatement Consulting
   
  Building Uses:
> Nanofabrication
> MOCVD
> Characterization research activities
   
  Key AGI Personnel:
> Abbie Gregg Cleanroom and Lab Consultant
> Craig Rossrucker – Cleanroom Consultant
> Mark Winter, PE CSP – Senior Technical Staff, Process, Safety Lead
> Michael Hillebrand, PE- MEP Engineer
> Ciel Villawatkins – Senior Process Engineer
> Michael Loontiens – CAD Technician